Every organization carries costs that keep the whole enterprise running but cannot be tied to any single program. The finance office. Executive leadership. Human resources. The building. The technology everything depends on. Those are indirect costs, and federal funding is designed to help cover them. Before you can recover them, you have to be able to tell them apart from direct costs, and defend the line you drew.

The good news is that the distinction comes down to one question you can ask about almost any cost. The harder part is applying it consistently, because the same kind of cost can land on either side of the line depending on how it is used.

The one question test

Ask whether the cost serves one program or many. One is direct. Many is indirect.

Direct and indirect, in the Uniform Guidance. Under 2 CFR 200.413, direct costs are those that can be identified specifically with a particular award or activity, or assigned to it relatively easily with a high degree of accuracy. Under the definition in 2 CFR 200.1, indirect costs are incurred for a common or joint purpose benefiting more than one cost objective, and are not readily assignable to the objectives they benefit without effort disproportionate to the results.

That last phrase matters. A cost is not indirect because it is administrative, or because it is hard to love. It is indirect because tracing it to each program it serves would cost more effort than the precision is worth. The electric bill for a building that houses five programs could, in theory, be metered program by program. In practice, nobody should, and the regulation does not ask you to.

What it looks like inside a local government

Run the test across a typical city and the answers sort themselves quickly.

Applying the test

  • A project engineer assigned full time to a federally funded road project serves one cost objective. Direct.
  • Asphalt, signage, and contractor invoices for that road serve one cost objective. Direct.
  • The finance director who processes payables for every department serves many. Indirect.
  • City hall's utilities, insurance, and information technology serve many. Indirect.
  • A grants coordinator who tracks every award the city holds serves many. Indirect, unless the coordinator's time on one award is specifically identified and documented.

Nonprofits see the same pattern on a smaller scale. A case manager assigned only to one funded program is direct. The bookkeeper who keeps the books for every program, the executive director, and the shared office are indirect.

A cost is not indirect because it is administrative. It is indirect because it serves many, and tracing it to each one would cost more than the precision is worth.

The same cost, two answers

Here is where organizations get into trouble. The Uniform Guidance recognizes in 2 CFR 200.412 that a cost can be direct in one setting and indirect in another. What it does not allow is treating the same kind of cost both ways in like circumstances. Each item of cost incurred for the same purpose has to be treated consistently, either as direct or as indirect.

The clearest example is administrative and clerical salaries. Those are normally indirect. Under 2 CFR 200.413(c), they can be charged directly to an award only when all of the following are true.

When administrative salaries can be direct

  • The services are integral to the project or activity.
  • The individuals involved are specifically identified with the project or activity.
  • The costs are explicitly included in the approved budget, or have the funder's prior written approval.
  • The costs are not also recovered as indirect costs.

That fourth condition is the one that catches local governments. A clerk whose salary sits in the cost pool behind the city's indirect rate cannot also appear as a direct line on a grant budget. That would charge the same cost twice. If the clerk truly works on one award in a way that meets all four conditions, the time on that award comes out of the pool and goes on the budget, with time records to prove it.


Why the line matters for recovery

The direct and indirect line is not bookkeeping trivia. It is the foundation of your indirect cost rate. A rate is built by dividing a pool of indirect costs by a base of direct costs, so every cost that lands on the wrong side of the line distorts both numbers at once. Put a direct cost in the pool and your rate rises on a cost that should have been charged to one award. Leave an indirect cost out of the pool and your organization absorbs a real cost it was entitled to recover.

That is why the work of sorting costs comes before any rate decision. How your indirect cost rate is calculated walks through the pool and the base, and where the indirect rules stand covers the de minimis option and negotiated rates. If the vocabulary is new, the NICRA vocabulary every local government and nonprofit should know defines every term you will meet along the way. And if your organization is weighing a negotiated rate, understanding NICRAs for federal funding is the place to start.

For the case behind recovering indirect costs at all, our episode on whether federal indirect cost rate cuts affect you explains what sets your rate and what protects it.

Sorting direct from indirect is the first decision in recovering the real cost of your work, and it rests on one question asked consistently: does this cost serve one program, or many. Answer it the same way every time, write down how you answered it, and the rate built on top of that sorting will hold up when a reviewer recomputes it.

Download Indirect Costs and NICRA, Decoded, the free guide that walks through the direct and indirect line, the de minimis election, the modified total direct cost base, and what a negotiated rate proposal actually requires.

Back to Blog

Get federal funding insights every Friday.

View our Privacy Policy and Terms and Conditions here. © 2026. All Rights Reserved.